Roof coverings and accessories by roof zone
Build a roofing request that separates the covering, underlayer, edge pieces and penetration flashings. Describe each roof zone against the current roof plan so suppliers quote only the material scope the project actually needs.
Start with the right material groups.
Covering sheets and tiles
List the roof covering by zone, profile, finish and fixing requirement. Distinguish new roof areas from refurbishment and removal scope.
Underlayer and separation
Identify membranes, vapour controls or separation layers that sit under the visible covering. State whether each layer is part of the roofing package.
Edges, ridges and penetrations
Break out ridge, verge, eaves, valley and penetration pieces from the area rate. Ask suppliers to price these against the same detail references.
A material price is only part of the package.
One schedule, clearly separated scopes. This is a request outline, not an installation drawing.
Included materials
Identify each roof surface by zone, covering type, finish and measured area from the current roof plan or elevation.
Connections & interfaces
Allocate ridges, verges, eaves, valleys, flashings and penetration components to the roofing package or to named separate packages.
Confirm separately
Confirm whether roof substrate repair, existing covering removal, access equipment and installation are included in the supplier's quoted scope.
Six details that make offers clearer.
- Product designation and format
- State the exact covering product, sheet or tile format, and the project-prescribed thickness or profile.
- Roof zone and substrate
- Identify the roof area and the supporting build-up so suppliers can respond to the installed condition.
- Detail revision reference
- List the roof detail drawing numbers and revision dates that apply to edges, valleys and penetrations.
- Performance requirements
- Request project-specific performance evidence for the proposed covering and underlayer combination.
- Accessories and flashings
- Separate ridge, verge, eaves, valley and penetration pieces with their measurement units.
- Quantity basis
- Ask suppliers to show net roof area, cutting allowance, laps and any waste allowance separately.
| Item & description | Quantity |
|---|---|
| R-01Profiled metal roof sheets for roof zone A; finish and profile per roof schedule. | 460 m² |
| R-02Ridge and verge pieces for roof zone B; profile and finish per current ridge and verge details. | 72 m |
Example quantities only; no live prices or supplier offers. Use your project schedule for final values and ask suppliers to list deviations.
Three checks before you decide.
Area rate and accessory completeness
Check whether edge and penetration pieces are included in the area rate or priced as separate measured items.
Underlayer scope
Confirm which membranes and separation layers remain in the roofing package and which move to a separate supplier.
Existing roof condition
State the removal, repair or overlay assumption used by each supplier so quotes are based on the same condition.
Details worth clarifying early.
Should underlayers be quoted with the roof covering?
Yes, if the project requires one supplier to coordinate the visible covering and the underlayer. State the required layer sequence so quotes are comparable.
How are roof penetrations listed in an RFQ?
Itemize each penetration by type and roof zone, and reference the current flashing detail. Avoid hiding them inside a general square-metre allowance.